Work to be Undertaken
Leachate line replacement
Start Date
Week commencing 21 June 2010
Cell Reference (see link to map below)
4A and 3A
What time of the day and night will you be carrying out the work?
During operational hours (Mon-Fri 07:00-18:00, Sat 07:00-13:00)
Why?
To allow works to sidewall to be completed
How long will it take?
Approximately 1 week
What might residents notice?
You may notice some plant movement and odour associated with the works.